CB-2198

Two Bathrooms, One Wall

Two back-to-back bathrooms rebuilt around one shared plumbing wall, with new venting and heated floors.

Primary bathroom with a green vanity, brass fittings and a marble-look glass shower

Job file

Project no.

CB-2198

Service

Kitchens and bathrooms

Location type

Duplex

Scope

Primary and guest bathrooms rebuilt back to back, new venting and heated floors

Duration

7 weeks

Floor area

190 sq ft

Budget band

$70k–$80k

Year completed

2024

The brief

Both bathrooms leaked into the floor below and neither had a working fan. The owners wanted them rebuilt properly, one at a time, so the house always had a working bathroom.

How we built it

We rebuilt the shared wall first with new supply, drain and vent lines for both rooms. Each bathroom was then waterproofed, tested and tiled in turn.

At handover

Both rooms were finished in seven weeks. The waterproofing was flood-tested before tiling and the results are in the handover file.

Guest bathroom with marble-look wall tiles, a double vanity and hexagon floor tiles
Green double vanity with brass faucets and arched mirrors in the primary bathroom